Long Earth Tubes

0

Posted on September 6, 2014 by

While the trench was open, it was our chance to lay the drain tile and earth tubes.  We didn’t set the timelapse and we were too busy working to take many photos, but it is an important step for any earth sheltered home, so I want to capture a few details.  Sorry, no timelapse.

We had already laid the drain tile and earth tube close to the house as we back-filled that portion. Click here for that story.  But we still needed to run long tubes from the house to daylight.

The bottom of the trench was already sloped to 1% and the septic line, made of 4″ schedule 40 PVC, was already in place (done by the excavator and already approved by the plumbing inspector).  We needed to bury it, but with a constant slope.  Sherri and I used shovels and rakes to pull down dirt and bury the original line by about 6 inches.  We (and the boys) stomped on this layer to pack it down, especially next to the buried septic pipe.  The end result was a nicely sloped flat bottom trench.

We connected 100 ft long segments of 6″ corrugated drain pipe to the ends of the pipe we had already buried up by the house.  We used a proper fitting connector piece and also taped it heavily and covered the connection in landscapers fabric.  We laid these two parallel drain tiles along the trench and periodically placed dirt on them to even everything out and keep them separated by a couple feet.  I would have liked to have separated them by more, and I did where the trench was wide enough.  In all, we added about 150 ft of pipe to each end of the drain tile loop.

Normally, a drain tile loop is connected to a single long pipe that runs to daylight.  However, by connecting each end to its own pipe, I am able to use it as an earth tube circuit with an inlet and outlet or two inlets.  The other end of the pipes goes into the house, but I can simply connect those ends together if I want the air to circulate under the mass of the house without entering it (by-passive annual solar heating).  The extra cost is the additional 150 ft of pipe, which cost me about ~$100.

2014-09-07_Tubes

 

The second layer of earth tubes was the 8 inch double wall (smooth inside) HDPE pipes.  These come in straight 20ft segments that have a bit of flex to them.  You can connect the pipes directly (bell and spigot ends with soil tight connectors) or you can connect them with 30 or 45 degree joints.  It was a hot day and we did not have the energy to properly bury the 6″ corrugated drain tile before laying the larger earth tubes, so we decided to mount the larger earth tubes to the side of the slope (with stakes) a couple feet above the previous layer.  This still left more than 10 ft of earth above these pipes for most of the distance and gave us more than 6 ft between the two parallel pipes.

2014-09-07_Tubes2

At the end of the day, we had 4 earth tubes, each over 150 ft long, going from the house to “daylight” along the trench.

The next step would be backfilling.

Later, while back-filling the trench, we made sure that the 8 inch pipes stayed in place while the excavator back-filled below/between them and the 6″ pipes…  This took some care and probably added at least an hour to the back filling process.  The excavators charged by the hour, so that should probably be counted in the cost of the earth tubes, but seemed like a bargain compared to backfilling that trench manually on that hot day.  I did pull out some of the stakes when they were no longer needed to hold the pipe still, but many were buried in place at an additional cost.

Leave a Reply