Tag Archives: Quonset

Rebar and Shotcrete over the Quonset Hut

5

Posted on July 15, 2016 by

Part of my earth sheltered home design included burying a Quonset hut.  Actually, this was the easiest and cheapest part of our build and if we had done the whole house this way, we might have been done the first year.

This post is for phase 3 of building our earth sheltered Quonset hut.  In phase one, we put up the steel Quonset (with a little help from our friends).  Phase 2 was getting up the Fox Blocks ICF endwalls.  That part was interesting, but took more time (and several posts).  We chose ICFs for the endwalls because they made the transition from wall to parapet for retaining the earth very straight forward.  Wood end walls would probably have been cheaper and faster, but not nearly as durable..

I have seen Quonset huts buried directly (with just a pond liner for waterproofing), but I wanted to put in a layer of reinforced concrete first. Phase 3 is to cover the quonset in reinforced concrete before we can bury it in phase 4.  (actually, I guess there was a waterproofing step before we can bury it also).  In this way, it is really the reinforced concrete that supports the earth load.  The Quonset hub becomes fancy form-work and an interior finish.

Here is the video about phase 3.

The Video:

Information:

Hot:  The day we put the insulation and plastic on the roof was officially the hottest day on record for our area…  The reflective Quonset hut was making it feel twice as hot and the heated metal was melting the duct tape that we used to tape down the Styrofoam. I edited the water breaks out of the timelapse, but they were about every 15 minutes.  Fortunately, we got clouds and cooler weather for the second half.

Crew:  Just  a quick note that I appreciated all the help I got on this portion of the build, both amateur and professional.

Rating:  My Quonset is rated for 75 lbs per square ft.  I am sure the engineers were thinking snow load and not concrete, and there is probably a significant safety factor built into that.  Either way, I am sure I significantly exceeded the official rating by about 50 lbs/sqft. Fortunately, my shotcrete was also sitting on the footings, shotcrete above that was really sitting on the shotcrete below, etc. The stiffening shotcrete really formed an arch from footing to footing and is probably not loading the Quonset hut significantly. Maybe if all the concrete were wet (no internal stiffness) at the same time, we might have had a problem, but instead, the shotcrete was curing and carrying load as it was applied.  Spreading the shoot over the 3 days probably helped.

Crenelations:  The Quonset crenelations (groves) were about 7.5 inches deep.  Across the top sections, we decided to fill with polystyrene strips 4 inches thick, 10 inches wide and 24 ft long.  Some quick math, and I can tell you that we placed more than 7 cubic ft of Styrofoam in each groove, which means we reduced the load on the top of the roof by about 1000 lbs per groove.  There were 20 grooves, and I filled 16 with Styrofoam, so that is a 16000 lb reduction.   I left 4 of the crenelations without Styrofoam (and added extra rebar) so they would have stronger hoop beams across.  We filled the concrete to a depth at least 4 inches above the crenelations, so the concrete in the crenelations was nearly 12 inches thick.

Plastic: The plastic liner was primarily to keep concrete from directly contacting the Quonset, and secondarily to provide an extra waterproofing layer.  I wasn’t fanatical about it.  The plastic is tough, but not impervious to puncture.  I have heard of people using pond liners with a heavy felt underlayment, or even grinding down all the bolt ends that could puncture the plastic.  Pond liner and underlayment can easily cost more than 50 cents per square ft (and the Quonset surface is well over 2000 sqft).  Our 6 mil plastic sheet cost less than 1/10th of that, so when it got a few little holes and tears I didn’t worry about it too much.  I had thought that the plastic would make it more difficult to walk around on top of the Quonset (because it could slip), but actually, it improved the walking conditions quite a lot.  I sagged the plastic to allow it to properly fall into each crenelation when the rebar and concrete were added.

Openings: The Quonset hut is a nice strong shape to work with (mine was an “S-Type”, the “Q” type would have been even better, but less practical without the straight stem walls).  Loads are transferred around it like pressure on an egg.  As you know, any crack in an egg weakens the overall structure tremendously.  I planned to have 3 openings in my Quonset shell, two skylights and a side door (to the mudroom). The most stressful time for the Quonset would be when it was covered with 46 yards of wet concrete (186,300 lbs) and two tons of rebar.  You do not want to have holes in the Quonset at that time.  Instead, I just created bucks to keep the concrete out of these three areas.  Later, I can come back and cut the Quonset steel with a grinder to make the openings.

Rebar: Each crenelation got 4 pieces of #4 rebar.  One vertical piece was “inside” each crenelation, centered and about 4 inches from the inner surface.  The other verticals were at a layer about an inch past the outer surface of the Quonset hut, spaced 8 inches apart.  The horizontal rebar was mostly tied to the outside of the vertical rebar and spaced no more than 12 inches apart.  Some horizontal pieces were placed first, against the surface.  These first horizontal pieces made it easier to place the outer layer of vertical rebar without things falling inside the crenelations.  They were kept off the Quonset hut by placing a few 1.25 inch rebar chairs (according to code).  We wanted most of the horizontal rebar further out where it could help hold more shotcrete up.

The other important rebar code section to worry about is overlapping the pieces.  We had a 40 ft long Quonset hut with 20ft long pieces of rebar.  I just placed them end to end and then came back later and tied 4ft long segments along that seam.  That was more than enough to overlap both sides by 40 diameters (code).

Electrical and Plumbing: I didn’t include it in the video, but we also ran plumbing and electrical before adding the shotcrete.  These were then inspected.  Part part of this was running white vent tubes up the side of the Quonset so they would come up the skylight curbs.

Balance: The Quonset hut shape holds even pressure very well.  It will actually get stronger when I put the balanced earth load on top…  But while applying dynamic load (such as the shotcrete) it is important to apply it evenly to both sides so the Quonset hut isn’t pushed flat.  Our shotcrete was poured over 3 days.  The first day got most of the short vertical walls done (our Quonset hut is an “S type”).  This stabilized the base and got us ready for the second day where they added most of the shotcrete, including filling some crenulations all the way across.  In the video, you can see them working one side and then the other, back and forth.  This required moving the heavy hose, which is tiring.  They made their lives a little bit easier by toeing the hose with the lift whenever they could. Then the crew left for the weekend (not ideal) and came back on Monday to finalize the top, add the shotcrete for the skylight curbs and do a final coat for smoothing.  All this time was partially because they also shot the bedroom at the same time (upcoming post), but planning to shoot things in a balanced and paced way is a good idea even if you could shoot faster.

The Compressor:  The shotcrete is moved to the wall in two ways.  The mix truck dumps the concrete into a hopper where it gets pumped (by a very expensive concrete pump) thru the hose to the nozzle.  In the nozzle, the “nozzle man” injects compressed air to blast the concrete at the wall.  Part of the magic of shotcrete (the strength, lack of cold joints, etc.) comes from the way it impacts/compacts the wall particle-by-particle.  Unfortunately, the compressor broke down soon after starting on the Quonset hut and somewhat spoiled the day (but somehow didn’t reduce the cost).  Ironically, this same compressor had broken down when they did the basement shotcrete, which was the last time the crew had come out.  They already had a concrete truck on site with 8 yards of concrete in it, so we decided to pump it out.  I knew that this wasn’t quite ideal in terms of speed of application or strength, but it did work and I didn’t have to worry about cold joints, since it was the first bit to be applied.  The next day, they rented a nice new compressor for only 60$ / day and it ran flawlessly.

Hard work:  Pretty much everything about shooting shotcrete is hard work.  Moving the hose, aiming it all day, keeping everything flowing, finishing the surface, repairing any issues with the equipment, cleaning up, loading up, moving scaffolding, etc.  It is all hard work and I appreciate the effort of the crew. Certainly I would suggest anyone think twice before deciding to take on this part of the build themselves.

 

Gallery:

These are pictures taken from my cellphone or time-lapse screenshots…  Enjoy.

Finishing the Quonset Hut

0

Posted on October 24, 2015 by

The Video

Its a short one this week, and the end is rather abrupt, but here it is anyway…

 

Why a Quonset hut?

My house design is an experiment with a variety of different arch forms.  Since it is a self build, I kept most of my spans shorter than 15 ft.  The exception is the garage.  I wanted a 3 car garage for practical purposes and decided to use a Quonset hut to form the wider span.

The quonset hut could probably support a significant earth load, if it were carefully distributed, etc. But in my design, it is really just fancy formwork to hold up the rebar and shotcrete that will actually support the earth.

My build also required a workshop to build the other components, and the Quonset hut is something that could be erected quickly, early in the construction, and provide that place.  I have used it to weld steel arches, store materials, and most importantly, to form my large concrete ribs.

Why build it in two stages?

The rib forms needed to be built on a large flat surface, out of the weather.   But we would also need to use a crane to move them to where they needed to go.  The ribs weigh 5000 lbs each, so I couldn’t roll them out across the gravel or dirt.  Instead, I needed to keep them on the slab, but also needed open sky above them for the crane.

The solution was to build only 2/3rds of the Quonset hut on the slab floor.  I could use that sheltered space at the back to form the ribs.  I would then jack them up and pull them forward to the open 3rd where a crane could lift them up and over to where they needed to go.

RibPulledOut

 

RibStillIn

When the crane came out, it did lift them straight up and over, but I noticed that it actually had a telescoping arm.  I asked the operator and he said that he could lift them up and pull them out of the building if I finished it…

The ribs were taking me a long time to make and closing off the building would save me a lot of hassle, so that seemed like a good idea.  It had been almost a year since the first 2/3rds were erected.

The final 3rd

My parents came down to visit and to pick up their camper. Anyway, it was windy and we didn’t want to try erecting Quonset sections with just the three of us. However, that is a good number for assembling the steel arches, so we spent most of the afternoon doing that.

SteelArchAssemblyParents

 

The following week, I put out help requests on Facebook and at work. The first few days, I was worried that I wouldn’t have at least 4 people there at one single time.  By the end of the week there were lots of people volunteering and I was buying a few extra half inch sockets and wrenches so there would be tools for everyone.  One co-worker even volunteered his whole family of very capable teens.

Bee_Bolting

Bee_ReadytoPull

 

The steel ribs went up very quickly.  7 in under two hours.  We were actually done before the Pizza lunch I ordered arrived.  No worries, we had other work to do (not captured on film).

Mistakes

Because these new steel arch sections were were bolted to the rest of the Quonset hut, which was already bolted and concreted to the slab, and because they were very heavy, I wasn’t too worried about the new section blowing away. With 13 people working in parallel to bolt the sections together, I didn’t want to interrupt that flow and make everyone stand around while I drilled and bolted the steel sections down.  I figured I would come back and take care of the anchor bolts next time…

However, by the next time I went out there, I found that the wind had lifted the front third of the Quonset out of the groove.  We ended up wasting several man hours and a lot of sweat getting it back into place.

OutOfGroove_1

 

OutOfGroove_2

OutOfGroove_3

I should have known better because this is a pretty typical fluid dynamics problem that I had to do several times at school.

QuonsetFlow

Another “mistake” that I pretty much accepted was that my building was a little longer than it should have been and ended up hanging over the edge by a few inches.  I ended up cutting that off so it wouldn’t get in the way of the end wall, but that is another story.

Footings are done

2

Posted on June 19, 2014 by

Steel Ordered

StudRite-product500pxWell, I managed to get the steel studs ordered this week.  I had to pay the 20% higher price then the previous quote from the other distributor (who ended up unable to get me the MarinoWare studs because they only ship when he has enough orders to fill a truck).  Anyway, this first order of studs for the basement isn’t very large and the difference was really only a few hundred dollars, so I pulled the trigger and ordered.  They said it may be delivered as soon as tomorrow.

Joe is walking down the street and passes a new butcher shop with a sign in the window that says “Sirloin Steak; 5¢ per pound”.  He goes in to buy some stake, but they are all out.  So he heads over to his regular butcher.  “Hey Mac, your competitor down the street is selling steaks for 5¢ per pound.  Can you match it?”   The butcher smiles, “That’s a great price Joe. Did they have any left?”  Joe says, “No, they were all out.”   “Well”, says Mac, “When I am out of steak, I can sell it for 4¢ per pound.”

 

In the meantime, I ordered the track and metal lath separately (from the cheaper distributor) and will pick that up, with my new trailer, Friday morning.

I am buying my Quonset hut from SteelMaster Buildings.  I heard that June 16th was the last day to get the 2013 steel prices, so I called and managed to get a great deal.  I had budgeted for the list price of about $10,000, but I managed to get it on “sale” for $7200, including all the nuts and bolts and delivery and the kit to connect it to the ICF end walls.  That is not bad for more than 4000 lbs of galvanized 22 gauge steel.  They will hold it in their warehouse and deliver it when I need it.

S30-15x40

This is a construction photo for the same size and type as what I ordered (S-30-15×40).  We will need to have a steel raising party ;^)  I will end up building the end walls out of ICF forms.

Footings are done.

It has been nearly a week since we poured the footings. The forms have been stripped. But the site was a bit of a mess (chunks of concrete, cigarette packets, nails, etc.)   I wanted to return things to the nice soft sand situation I started with, so I took an hour and cleaned things up.  I dumped all the concrete chunks in one section of the footing where no one was likely to walk.  The wood scraps made a very small pile of kindling and I had a bucket of trash dropped by the crew.

I got out my cell phone and made a quick video to show you where we are.

The exposed aggregate finish looks kind of nice, and will give the shotcrete something to grip, but it may be a bit of a bumpy hassle for laying the track.

The bleeder pipes were made of flexible corrugated drain pipe nailed to either side of the forms.  As the heavy concrete was poured, the light weight pipe floated up in the middle, which is probably not ideal at all.  The guys pouring the concrete made brief attempts to hold it down by stepping on it.  Next time, I will bring my own 2ft sections of rigid PVC so I can get the slope I want.

The concrete bulged in a few places and some of the edges were a little rough, but overall, it worked out nicely…

Funny thing is, I am still waiting on a bill.  I have not paid a cent yet.  I actually texted Doug today asking if they would send a bill so I can pay it.  I am more eager than usual to pay because anything I can pay out before we close (next Tuesday) means I don’t have to bring an extra 10% (safety factor) to closing.

SwallowEgg_croppedSome of you may have noticed a section of the swallows nest collapsing in the rain during the last video, click here to jump to just before the sand collapses.  Did anything bad happen to the swallows?  Well, I didn’t find any dead birds, but I found an egg…  Oh well.

The building inspector said these swallows were great for eating the bugs flying around the site.  I just hope the excavated sand holds up until the little birds are ready to fly.

Steel Shipping Container

Since my construction site is so far from my home, I needed a way to lock up construction equipment (generator, welder, table saw), supplies, etc.  I ended up deciding that a 20’ steel shipping container would be a pretty good idea (thanks to John H. for the tip).  They are pretty cheap ($1300 to $1600), so I was tempted to buy one (and later bury it), but I got such a great price on rental (79$/month, which is less than half of what others were charging) and delivery from MACs Storage Containers in Lansing that I couldn’t justify buying one…

I had leveled the “perfect spot” across the driveway from the rest of the construction site.  But the sand on either side of my driveway is very soft and the heavily loaded tilt truck was just tearing it up.  It was quickly stuck up to its axels.  Eric, the delivery guy from MACs, started “unloading” where he was, on an uneven spot of sand half overlapping the driveway and pretty much in the way of all the future trucks that would be coming thru.  I thought, “Oh well, now I really need to buy a tractor so I can drag this into a proper location.”  But it turned out that Eric was just using the tilt bed like a clams foot to push the truck out of its hole and try again.  He tried a couple other approaches as I looked hopefully on.  Eventually, he asked if I minded him driving on the grass behind the spot, I didn’t.  But to make that work, he would need to turn the container around so the door would be on the right side.  He slipped it off, drove the truck around and scooped it up again with evident expertise, which I always appreciate in anyone I work with.  After that, the delivery was easy and he was out of there quickly.

I will probably need to go and jack up the the front left corner a bit to level it out before I move in.  I will also need to buy a couple locks.   The container has 4 vertical locking bars so it is pretty secure (unless the theif has a tilt bed truck like Eric).  It smelled a bit musty inside, but it has the secure storage space I need.  John also gave me the idea of putting a tarp off the one side for a shady place to work.

Here is a video of the delivery, just because I could.

Next steps

Friday (June 20th), I plan to put the basement door bucks together and head out there to lay the basement track.   My vertical studs may arrive and so I can start to go vertical on Saturday.  I still need to buy some scaffolding, but I will take my 15 ft ladder for now and start with the shorter pieces.